Complete retubing of auxiliary boiler KAV - 6,3/16
08/05/09 Complete retubing of auxiliary boiler KAV - 6,3/16 on board the tanker vessel under DNV class. Description of works: - preparation of boiler retubing procedure and approval by DNV CS; - purchase and fabrication of full set of tubes according to the original drawings; - transportation of the tubes to the vessel; - renewal of tubes (downcoming, convention bank, screen bank) during vessel operation; - pressure test of the boiler; - handover of the boiler in operation to CS representative.
|
|
||||||